Project Detailsx
Project Overviewx
PROINSO Group is proud to announce the successful completion of a 2 MW solar energy project for Golden Star Company Limited, a leading textile manufacturer in Vietnam.
Located in Truong Son Town, An Lao District, Hai Phong City, this installation marks an important milestone in Golden Star’s commitment to achieving NetZero emissions through energy‑efficient and sustainable power solutions.
Project Detailsx
Commission Date: August 28, 2024
Solar Capacity Deployed: 1 MW (with full capacity to reach 2 MW)
Expected Annual Energy Generation: 1,062,000 kWh
Solar Modules: Jinko JKM555N-72HL4 (555Wp)
Rooftop Structures/Trackers: Clenergy
Inverters: SMA CORE2 STP 110-60 (110kWac)
EPC Contractor: H2t Hanoi
Project Developer: ETIAM Insights-KIVN (Kaizen Institute Global Vietnam)
Project Impactx
This solar installation significantly supports Golden Star’s long‑term sustainability strategy while reducing operational energy costs. The project demonstrates the rapid adoption of renewable energy within Vietnam’s textile sector, setting a new benchmark for industrial decarbonization.
PROINSO Group is honored to contribute to this forward‑thinking initiative and remains committed to delivering high‑performance solar projects that drive sustainability, efficiency, and economic value for our partners.